11 m All-in-One Solar Street Light

Plan a trial before converting a row of 11 m poles to integrated solar lighting. Compare retained positions, justified layout changes and an independently mounted panel where needed.

SL-AIO-HC all-in-one solar street light for municipal and EPC projects
SL-AIO-HC integrated light and mounting position.

Approve one trial section before the next batch

Compare the HC and DR with their actual optics on the same trial section. Record the approved lens, mounting angle and controller settings for the next delivery.

SL-AIO-HC integrated solar street light system and component views
Series view

SL-AIO-HC · 100 W

Integrated solar panel and battery

Compare the 100 W project configuration on the trial poles and confirm the selected optic, panel and battery.

Send the trial criteria and the equipment you intend to buy

Send first

Share the proposed pole spacing, the road section, the mandatory technical clauses and the sample deadline. State who signs the trial and who can approve any change after it.

What to check

Compare the proposed HC and DR candidates on the same trial section with the optics under offer. Ask for the fixture, IES, mounting and controller references in a signed trial record.

Freeze the 11 m trial configuration before comparing later deliveries

For an 11 m public road, take the HC and DR candidates through the same trial section with their actual lenses. Include the widest or most demanding representative geometry you intend to repeat. Start an approval record that can be handed to both purchasing and the team who will test the delivered batch.

Control pointRecord for the next order
Lighting comparisonProduct and lens code, IES version, position grid, mounting angle and simulation result.
Installed trialRepresentative pole ID, photos of the interface, night settings and any agreed adjustment.
Batch inspectionApproved part identifiers and configuration revision used to compare the received equipment.

If the supplier proposes another optic or changes the controller profile after the trial, list the effect and the result that must be confirmed again. Keep the baseline signed off by the project team and accessible to whoever receives the next batch.

Other Sunlurio options to compare

SL-ONE-DR six product illustration

SL-ONE-DR · 100 W

6 LED modules · 150 Wp panel · 857.6 Wh nominal battery · Ø80 mm mounting interface

Compare the drawer-battery option when maintenance access matters. Check the two exact optics and the night programme on the same road layout.

What makes an 11 m trial useful for purchasing

  • Lighting approval. Record the tested IES, lens, mounting height and tilt. Include the far edge and darkest span on the same calculation grid. Request the matching photometry
  • Repeat-order approval. Link the accepted sample to the head, driver, battery and dimming revision. Agree what must be tested again if any of them changes. Review inspection evidence

Decide what the trial should settle

An existing row of 11 m poles can make an integrated solar conversion worth investigating. The first question is what the project needs to prove before buying a full batch. Name the constraint most likely to rule out a proposal, such as a long gap between poles, exposed site conditions, poor charging orientation or a difficult position to service. Collect the current road layout, pole records and site use, then choose which alternatives to compare. A good trial should tell the owner whether to keep the positions, change parts of the layout or assess a different system.

Agree whether 11 m means the existing shaft, the top fitting or the emitting centre. A drawing from another pole family can have the same height and completely different attachments. Mark the actual installed view, bracket and road dimension reference. If the existing poles also carry equipment, give the reviewer the full arrangement rather than a close-up of the light alone. Identify one representative section and the positions that differ materially. Give both to the design team before the trial is set up, so the outcome can be applied to the correct parts of the project.

Trace the 11 m trial from the test sheet to the delivered carton

We use one trial record as the purchasing reference. Keep the test output, lens code and mounting set next to the approved sample ID. When a batch arrives, the receiving team should be able to check what changed without reconstructing the original comparison.

CheckWhat to agree or verify
Before the trialRecord the exact model and optic, file identifier, physical mounting angle and controller schedule. Ask for the right grid and approval limits for the test road.
At the first deliveryMatch the fitting marking and carton reference against the trial sheet. If a different lens or controller programme is offered, review the affected performance before accepting it.
After the first nightRecord the measured positions and any agreed deviation against the sample. Keep a separate acceptance entry for the physical fit, the light output and the programmed operation.

Put more than one feasible layout on the same brief

First test the retained geometry with a supported all-in-one candidate. The designer should use the actual pole positions, bracket direction and relevant setbacks. Ask them to show the result for the critical parts of the road using the specific optic and output in the operating schedule. The second option might change the head aim, bracket or the position of a few poles, subject to the project’s structural and civil review. A third option can use an independent solar panel where the positions that serve the road give poor charging orientation for an integrated surface.

Set comparison rules that apply to every option. Use the same site, required lighting area, agreed operating periods and applicable criteria. If one layout changes the geometry, state that change and ask how it affects construction and access. Put the proposed service conditions beside the lighting outcome for each option. Comparing the oldest pole arrangement at a reduced mode with a proposed layout at full output confuses two changes. Give the designer and buyer a way to see which difference the calculation or trial is testing.

Keep the integrated head and its installation constraints in view

For the light you intend to trial, ask for an installed assembly and interface drawing. Confirm which mounts, aims and orientations the supplier supports for the component combination. Confirm how the parts will be accessed for fitting and later replacement. Give the structure reviewer the actual head and mount geometry and weight, any existing attachments and available pole and foundation records. Have the responsible reviewer identify what conditions must be met before the trial is approved. A demonstration of the beam does not settle whether the existing structure can carry the revised assembly.

Show the photovoltaic position at the approved light aim, and review exposure at the actual locations and in the relevant season. A position on a drawing can appear unobstructed even where nearby trees or buildings shade the panel. Use site observations for any difficult poles. Give the energy reviewer the required light schedule and ask how the controller behaves under weak charging. The trial may be suitable to check installed orientation and selected modes now, while the worst-season charging result needs documentary support or an agreed later test.

SL-ONE-DR drawer product illustration
SL-ONE-DR battery drawer and housing.

Send the trial criteria with the tender clauses

Link the mandatory lighting and mounting requirements to the actual optic and sample configuration under review. Give the consultant the matched document references and record the approval or deviation decision against the corresponding tender line.

Collect a complete first-pole record. Alongside the trial readings, keep a photo and drawing of the head mount, base and any electrical connections required by the approved design. Confirm the local crew can repeat the installation as reviewed. Carry the same drawings into the rollout instead of asking later crews to work from the readings alone.

Engineer reviewing solar road lighting drawings and project document requirements
Engineering review of project drawings and document requirements.

Choose a section that makes the results comparable

Select a span that covers the point or function expected to be difficult. This may be the long span between two retained poles or a crossing on the far side of a road. Keep a nearby reference point where the existing arrangement and proposed option can be compared at known conditions. Confirm the installed lamp height and aim and place the agreed evaluation points on a sketch. Record the date, other sources operating nearby and the controller mode. Photograph the geometry from marked positions as a record that can be used when the crew returns.

Where two options are tried in the same place, agree when each runs and how the test team switches between them safely with the installer. Make sure the records show which source was on and whether the road and surroundings changed between readings. If two locations have to be used, write down the differences before comparing them. Ask the lighting reviewer to explain which differences can be separated from the change in the light. That makes it easier for an owner to decide what the trial actually proves and whether another test is needed.

Sunlurio goniophotometer photometric testing lab for street lighting IES and LDT review
Photometry equipment used to prepare luminaire distribution files.

Use clear accept, revise and stop decisions

Before the trial, agree what results let the owner retain the chosen pole group. This could include project-specific lighting criteria, solar feasibility and acceptance of the mounting and service arrangement. Define what happens if a single problem is found with an otherwise workable design. A different optic or a revised location can be proposed, reviewed and checked on the same basis. If the fit, road coverage, charging or safe access cannot support the required service, record what alternative should be examined instead of buying the same equipment for the full length of road.

Apply the outcome to each group deliberately. A trial on an open straight section may show the best case for the solar surface while a nearby shaded junction has a different energy balance. Make the limits of the result legible in the order plan. If only a subset is approved, identify those pole IDs and leave the other groups for review. Include the required aim and operating profile with the accepted option. A crew receiving boxes later should know which configuration to install at the sites represented by the trial.

Use the approved sample as the production comparison

Keep the fixture code, lens, bracket and controller settings in the trial record. On the first production units, verify the parts and the selected checks against that record. Record proposed changes while there is still time to review their impact.

Lighting product testing and quality control checkpoint before shipment
Photometric testing facility.

Give the buyer and the site team the same trial record

Ask the supplier for the proposed equipment list, design outputs and trial verification references. The list should identify the head, optic, panel and battery arrangement, controller settings and mount used on site. Give the owner the light calculation inputs, trial point record and relevant photographs, plus the status of any outstanding structural or energy approval. Write the recorded setting and version on the field record. A product list which only states a wattage makes it hard to reproduce the tested conditions or compare a spare later.

Where the first trial uncovers a problem, write it down in terms of what the owner observed and where it occurred. A poor far-side reading, an attachment outside the fitted mount or a reduced solar view each points to a different check. Ask the reviewer to log the input or part that was revised and the relevant result after the change. If the second test happens on another night, record the operating profile and other light sources again. The owner can then see which change made the difference.

When converting the approved option into an order, review changes between the trial unit and planned supply. A different optic, mount or controller version can affect one or more of the checks. Ask the technical lead to decide which evidence stays valid and which needs a targeted check. Make those changes before the repeated installation details are issued. At handover, include the accepted position schedule and enough information for the maintenance team to restore the tested aiming and working modes.

Lighting shipment cases and cardboard cartons staged on the workshop floor
Export cases staged before dispatch.

Keep the tender response tied to the trial and later batches

Keep clause numbers

Let the supplier reply by requirement and cite the relevant model or document revision. List deviations explicitly so the consultant can review them under the project rules.

Keep the approved sample traceable

Record the lens, brackets, controller settings and equipment labels that the receiving team can identify. If the project requires a sample, agree how the batch is compared with it.

Call out any changes before loading

Request a change sheet if a part or setting differs from the trial. Decide which drawing, calculation or field checks need to be repeated before accepting the change.

In Project details, give the sample date and the technical clause numbers. Tell us if you need a way to send restricted tender files.

Give receiving staff a copy of the trial approval

A road trial usually provides more detail than the purchase line. Carry the signed fixture, optic, angle and settings into the receiving copy, with the photos needed to recognise an approved item. If a different version is offered, agree who can approve the change and which checks need to be repeated before delivery.

Use the trial unit as the reference for receiving

We put the sample code, optic, controller programme and mounting orientation on the job’s approval sheet. The inspector should then be able to compare the delivered fitting and its carton with that same sheet, even if the finish and outer body look unchanged.

When reading a photometric report, match the sample identity, input and file version before treating its values as evidence. A similar intensity plot, family name or wattage does not establish that the offered lens was the tested one.

At the 11 m trial, record the actual light, optic code, tilt, observed dark points and any accepted deviation. If a later shipment changes the lens, housing or settings, ask what must be rechecked before repeating the installation.

Show the approved revision on the batch records

Ask the shipment file to connect the product labels, packing list and any inspection references to the configuration approved by the buyer. Keep replacement units and stock spares identifiable in the received quantity.

Set the commercial terms for trial and rollout. Where an order goes from trial poles to a full street, ask us to quote the trial and later releases separately. For each, show dispatch timing, what coverage starts from and how any replacement is handled. Keep the trial serial numbers and signed settings with the offer so the equipment used to prove the layout can be identified later.

LED street light packaging line with carton marks packing photos and shipment preparation
Carton marking and packing preparation.

Questions about trialling an integrated option at 11 m

Ask for a proposed configuration that matches the site and required lighting. At this height, give the supplier the actual positions, bracket and operating conditions first. Confirm the exact model, optic, head assembly and evidence before releasing the equipment. A supplier can often identify the first comparison without committing the site to the full installation.

Ask which questions a temporary arrangement can answer. A temporary height, aim or location can be used for a preliminary viewing if it is approved for that purpose. The final evaluation should reflect the actual geometry, equipment and agreed conditions. Mark any results that need to be checked again once those inputs are in place.

Select a representative span and any different condition that could change the decision. Pay attention to the gap, mounting or solar constraint that the road owner is most concerned about. If a few poles sit in shade or serve a different width, give them a distinct review rather than assuming that a trial on the simplest stretch covers the project.

Check that the old report shows the location, operating condition and criterion clearly. A common set of points can help compare options when the owner wants the same road service. Add points for any new area, such as a pedestrian crossing, and record any changed mode or ambient light while taking readings.

Send the pole layout and mounting records, the required lighting area, operating hours, case photographs and known access or solar constraints. Say whether the owner can move poles or change structure. We can use those inputs to identify what the first modelling comparison should show and where a trial would help settle the decision.

Use the verified pole groups and operating conditions to define the first release. For a later phase, compare its spacing, surrounding light, solar access and equipment revisions with what was trialled. A phased order can preserve the useful result while keeping untested positions open for the review they require.

Match the model and batch labels, mounting and the agreed lighting and control settings to the approved sample. Use the specified acceptance checks for the delivered batch and keep any approved changes with the inspection record.

Ask for the matching photometry and its impact on the weakest points of the trial layout. Approve the change against the recorded acceptance criteria before using it on the next batch.

Compare the exact optic, mounting and control schedule with the approved copy. Ask for a repeat of the affected review when a technical change alters what the trial established.

Plan My Retrofit Trial

Send the current road and pole layout, mandatory lighting and service conditions, and the positions that could be changed or tested.

PLANNING A SOLAR STREET LIGHTING PROJECT?

Share your project location, estimated quantity and requirements.
We’ll review the suitable configuration and supply scope for your project.