Côte d’Ivoire Road & Highway Street Lighting Project
Public Côte d’Ivoire road and highway street lighting reference.
Document support depends on confirmed project scope, product configuration, tender requirements and document stage.
| Country / Area | 🇨🇮 Côte d’Ivoire | Road & Highway (Multi-site) |
| Client Type | EPC Contractor |
| Procurement Context | Government Tender |
| Application | Road & Highway Lighting |
| Product Type | Split Solar Street Light |
| Quantity | 890 Sets |
| Lamp Power | 60W LED |
| System Architecture | PV + LiFePO4 Split Solar System |
| Pole Height & Spacing | 7m Poles | Project-specific spacing based on road layout |
| Controls | Dusk-to-dawn Operation + Programmable Dimming |
| Project Deliverables | IES-based Photometric Review / BOQ Alignment Support |
| Verification Basis | Lighting layout reviewed against the confirmed project brief and road-layout inputs |
| Project Year | 2023 |
Project Background
This multi-site road & highway deployment in Côte d’Ivoire delivered reliable lighting output with a split solar street light configuration. After installation, the roadway achieved clearer visibility and more consistent night-time coverage across key sections—while keeping assumptions verifiable for EPC and tender workflows. The reference includes documented layout inputs, IES-based optics verification, and BOQ alignment notes to reduce rework and speed up sign-off.
Technical Configuration (Typical Range)
- ✓ Roadway optics supported with IES photometric files for layout verification
- ✓ Typical mounting: 7m poles; spacing documented per section and target criteria
- ✓ Split solar system (PV + LiFePO4) sized by autonomy requirement and local conditions (configuration range available)
- ✓ Dusk-to-dawn operation with time-based dimming profiles (motion optional)
- ✓ 60W LED lamp reference; final wattage and optics mapped by road class
- ✓ Deliverables referenced: BOQ alignment + traceability notes for multi-site consistency
Scope & Assumptions
A concise summary of what this reference covers and the verification inputs behind it.
Scope (Multi-site Road & Highway)
- Coverage: multiple road and highway sections across Côte d’Ivoire (multi-site reference)
- Use case: EPC / tender workflows requiring verifiable assumptions
- Deliverables referenced: IES photometry + BOQ (layout notes on request)
- Configuration approach: roadway-optics based ranges aligned to site constraints
Verification Inputs (Assumptions Documented)
- Pole height: 7m (as referenced for this deployment)
- Lamp power: 60W LED (reference configuration)
- Spacing: layout-dependent, documented per section
- Optics: roadway distribution verified using IES files
- Targets: maintained lux & uniformity per project brief
- Site notes: dust sealing, cable glands, and label readability checked for acceptance
Verification inputs may be reviewed after project scope, disclosure level and document stage are confirmed.
Photos & Acceptance Notes
Field photos confirm the deployment is real. The notes below summarize typical site acceptance checks used by EPC teams to reduce rework and sign-off risk.
Acceptance Notes (Typical)
✓ Bracket / Arm Interface
Verified against drawings (spigot size, orientation).
✓ Wiring & Polarity
Checked before commissioning; glands sealed.
✓ Controller Label / ID
Recorded for traceability (batch/serial).
✓ Pole Verticality & Base
Checked after installation (base fastening).
✓ Dimming Profile
Applied and verified with timestamps (log/screenshot).
✓ Lux Spot-Check (Optional)
Performed on a representative section.
Tip: Full checklist and traceability tables can be shared in a redacted pack or under NDA.
Document Support Scope
Document support depends on confirmed project scope, product configuration, tender requirements and document stage. Browse public resource pages or request a project-specific review.

IES / LDT Photometric Files
Browse IES files used for roadway optics verification and layout checks. Suitable for EPC submissions and audit trails.

BOQ (Bill of Quantities)
Review BOQ examples aligned to scope, accessories, and configuration ranges for procurement and budgeting.

Drawings & Acceptance Checklist
Request drawing and datasheet review after product configuration and document stage are confirmed.

DIALux / Relux Outputs
See report samples and typical verification items (maintained lux, uniformity, assumptions, and result tables).
FAQ (Tender & Verification)
Quick answers to common EPC / tender questions for this reference.
What documents can be shared for tender submission?
We can share a tender-ready reference pack including IES photometric files, a BOQ reference, and key layout/assumption notes. Redacted versions are available to keep project details compliant.
Do you provide IES files and layout assumptions for verification?
Yes. IES files are provided for roadway optics verification, and we document the main assumptions such as pole height (7m), spacing logic, and target criteria used for checks.
How do you handle multi-site projects with different road classes?
We keep one documented baseline (optics + mounting interface + control profile), then adjust spacing/targets per section. Each section is tracked with consistent naming to avoid mix-ups.
Can you share photos and acceptance records under NDA?
Yes. Field photos, packing/label traceability notes, and acceptance checkpoints can be shared under NDA or as a redacted pack for tender review.
What inputs do you need to propose a similar configuration?
Road type/class, required maintained lux/uniformity, pole height & spacing, installation layout, autonomy requirement, and any tender standards. A CAD/sketch or Google map pin helps speed up confirmation.
Get in Touch with Sunlurio Manufacturer
Send Your Project Information for Review
Response time depends on project information completeness, BOQ / drawing availability and required document scope.